Valley Roadwork Schedule Sunday through Saturday January 4 - 10
LONG-TERM PROJECTS
State Route 32 (Butte County) Work continues on a $9.9 million project by the City of Chico to widen State Route 32 from two lanes to four lanes between Fir Street and El Monte Avenue. Completion is expected in 2015. No traffic-interfering work is scheduled.
State Routes 70 and 20 (Yuba County) Work is wrapping up on a $46.5 million project to replace sections of highway through Marysville with continuously reinforced concrete pavement, enhanced traffic signals, upgraded sidewalks and curbs and improved drainage systems. The project is scheduled for completion in early 2015. Throughout the year, motorists can visit www.mvforward.org for project updates and traffic alerts. No traffic-interfering work is scheduled.
State Route 70 (Yuba County) Work continues on an $18 million project by Yuba County and Caltrans to build a new interchange at the intersection of State Route 70 and Feather River Boulevard.
January 4 - 10
State Route 70 (Yuba County) between Feather River Boulevard and the Sutter County line: Motorists can expect the north- and southbound right shoulders closed through this spring.
State Route 99 (Butte County) Work continues on a $10 million project by the Butte County Association of Governments and Caltrans to replace the northbound bridge over Butte Creek. The project is scheduled for completion in 2015. No traffic-interfering work is scheduled.
State Route 99 (Sutter County) Work continues on a $62 million project to widen State Route 99 from two to four lanes by constructing a new bridge over the Feather River. The project is scheduled for completion by early 2015. No traffic-interfering work is scheduled.
State Route 99 (Sutter County) Work is wrapping up on a $31 million project to construct a full interchange at Riego Road. The project is scheduled for completion by early 2015. No traffic-interfering work is scheduled.
SHORT-TERM PROJECTS
Interstate 5 (Glenn County) at the South Willow Fork Creek: Southbound motorists can expect the #1 lane closed from 8 a.m. to 3 p.m. Monday for guardrail work.
Interstate 5 (Glenn County) at the Wilson Creek Bridge: Southbound motorists can expect the #1 lane closed from 8 a.m. to 3 p.m. Monday for guardrail work.
Interstate 5 (Glenn County) from County Road 39 to County Road 20: North- and southbound motorists can expect moving lane closures from 8 a.m. to 3 p.m. Tuesday for shoulder work.
Interstate 5 (Glenn County) from County Road 20 to the State Route 32 interchange: North- and southbound motorists can expect moving lane closures from 8 a.m. to 3 p.m. Wednesday for shoulder work.
State Route 20 (Sutter County) from the Wadsworth Canal to South Butte Road: Motorists can expect one-way traffic control from 9 a.m. to 2 p.m. Monday through Wednesday for guardrail work.
State Route 65 (Yuba County) from Oakley Lane to South Beale Road: Motorists can expect the north- and southbound #1 lane closed from 9 a.m. to 2 p.m. Tuesday and Wednesday for drilling work.
State Route 70 (Yuba County) from 24th Street to Cemetery Road: Motorists can expect one-way traffic control from 9 a.m. to 3 p.m. Thursday for guardrail work.
State Route 99 (Butte County) from East 5th Avenue to south of East 1st Avenue: Southbound motorists can expect the #2 lane closed from 8 p.m. to 4 a.m. Tuesday for electrical work.